# 4.7 Release History
| Name | Invitations | Reviewing | Testing | Release | Post Mortem | Planning Document |
| --------------- | --------------- | -------------- |----------------| ------------- | ----------- |-------------------|
|Feb-Mar Cycle (4.7.31)| | | Feb 7 - Mar 6 | Mar 7, 2018 | N/A | |
|Dec-Feb Cycle (4.7.30)| | | Dec 20 - Feb 6 | Feb 7, 2018 | N/A | |
|Dec Patch (4.7.29)| | | | Dec 20, 2017 | N/A | |
|Nov-Dec Cycle (4.7.28)| | | Nov 1 - Dec 6 | Dec 6, 2017 | N/A | |
|Oct-Nov Cycle (4.7.27)| | | Oct 6 - Oct 30 | Nov 1, 2017 | N/A | |
|Oct-Nov Cycle (4.7.26)| | | Oct 6 - Oct 30 | Nov 1, 2017 | N/A | |
|Sep-Oct Cycle (4.7.25)| | | Sep 6 - Oct 4 | Oct 5, 2017 | N/A | |
|Aug-Sep Cycle (4.7.24)| | | Aug 3 - Sep 5 | Sep 6, 2017 | N/A | |
|July-Aug Cycle (4.7.23)| | | | Aug 3, 2017 | N/A | |
|July Patch (4.7.22)| | | | Jul 12, 2017 | N/A | |
|June-July Cycle (4.7.21)| | | | Jul 6, 2017 | N/A | |
|May-June Cycle (4.7.20)| May 4 | May 5 - 12 | May 13 - Jun 6 | Jun 7, 2017 | N/A | [Signup Form](https://civicrm.org/civicrm-release-sign-up) [Release Management](https://civicrm.org/civicrm-release-management)
|April-May Cycle (4.7.19)| Apr 7 - 13 | Apr 13 - 18| Apr 19 - 2 May | May 3, 2017 | N/A | [Signup Form](https://civicrm.org/civicrm-release-sign-up) [Release Management](https://civicrm.org/civicrm-release-management)
|March-April Cycle (4.7.18)| Mar 13 - 19 | Mar 19 - 22| Mar 23 - 4 Apr | Apr 5, 2017 | N/A | [Signup Form](https://civicrm.org/civicrm-release-sign-up) [Release Management](https://civicrm.org/civicrm-release-management)
|February-March Cycle (4.7.17)| Feb 9 - 16 | Feb 17 - 23| Feb 24 - 5 Mar | Mar 8, 2017 | N/A | [Signup Form](https://civicrm.org/civicrm-release-sign-up) [Release Management](https://civicrm.org/civicrm-release-management)
|January-February Cycle (4.7.16)| Jan 9 - 16 | Jan 17 - 23|Jan 24 - 7 Feb | Feb 8, 2017 | N/A | [Signup Form](https://civicrm.org/civicrm-release-sign-up) [Release Management](https://civicrm.org/civicrm-release-management)
|December-January Cycle (4.7.15)| Dec 5 - 10 | Dec 10 - 15|Dec 16 - 3 Jan | Jan 4, 2017 | N/A | [Google Doc](https://docs.google.com/document/d/1cBRc2QQBIF3uEmBfbPrv-dxgM1LDLx-aL3OmaNmJQDM/edit?usp=sharing)
|November-December Cycle (4.7.14)| Nov 5 - 11 | Nov 11 - 21|Nov 22 - 6 Dec | Dec 7, 2016 | Dec 14 - 15 | [Google Doc](https://docs.google.com/document/d/107kGgGCQnsjPlGQqXUqO2P7u1mfdtnJ8EQ8pq_L7mIo/edit?usp=sharing)
| October-November Cycle (4.7.13)| Sep 19 - Oct 13 | Sep 19 - Oct 13 | Oct 14 - 29 | Nov 2, 2016 | Nov 9 - 10 | [Google Doc](https://docs.google.com/spreadsheets/d/1Kr4OuyMqKBCo5TOSf5CCIKv4vP5X0oT7K3jB7gDLQxg/edit?usp=sharing)
| September-October Cycle (4.7.12)| Sep 8 - 18 | Sep 8 - 18 | Sep 20 - Oct 1 | Oct 5, 2016 | |
| August-September Cycle (4.7.11) | --| Aug 16 - 27 | Aug 29 - Sep 4 | Sep 7, 2016 | | [Google Doc](https://docs.google.com/spreadsheets/d/1XSLoTNr6RKUvaydGPhdsQMT6orimub1AO1ZEbEe_Mp8/edit?usp=sharing), [JIRA Board](https://issues.civicrm.org/jira/secure/RapidBoard.jspa?rapidView=32&view=planning)
| July-August Cycle (4.7.10) | Jul 5 - 10 | Jul 11 - 19 | Jul 20 - Jul 29 | Jul 3, 2016 | | [Google Doc](https://docs.google.com/document/d/1UAFOy0gXar_ouzWgOpCdbMA2r6_sIyO_KPiZey9jVDE/edit), [JIRA Board](https://issues.civicrm.org/jira/secure/RapidBoard.jspa?rapidView=28&view=planning), [Calendar](https://calendar.google.com/calendar/embed?src=91qib0v17nu4oom8cv8vss9jp0%40group.calendar.google.com&ctz=US/Pacific)
| June-July Cycle (4.7.9) | Jun 9 - 14 | Jun 14 - 25 | Jun 27 - Jul 3 | Jul 6, 2016 | | [Google Doc](https://docs.google.com/spreadsheets/d/1fmHFOZ83ectSPCMWvXwCeJgrw4KpYi8JEV2ZDkd6XDU/edit?usp=sharing)
| May-June Cycle (4.7.8) | May 5 - 10 | May 10 - 18 | May 21 - 29 | Jun 1, 2016 | | [Google Doc](https://docs.google.com/spreadsheets/d/10EyNqm3-CbAwUjYzckrwSE7VjpZCfatzh-bES59XqA8/edit?usp=sharing)
| April-May Cycle (4.7.7) | Apr 5 - 8 | Apr 9 - 18 | Apr 22 - May 1 | May 4, 2016 | | [Google Doc](https://docs.google.com/spreadsheets/d/14j8YgFTeMneuLI7iKOBhZYu1i1oksvKLG47W7hYUwU0/edit?usp=sharing)
* **Invitations**: The release-manager curates the list of pending PRs and invites developers to partner-up based on related topics (such as a "CiviMail" group or a "CiviContribute" group). All members of the core developer team will participate.
* **Review Week**: Participants review each other's PRs. This may involve some discussion, code-review, testing, merging, or closing PRs.
* **Test Week**: Participants install the release-candidate with realistic configurations (eg staging sites) and check that their major customizations still work. Emergency issues (regressions) may be fixed.
(Note: This is a new process and may change for future releases.)