CiviCRM Release Management

This project supports meta-activities for release-management, such as the index of release-plans and the release invitations.

Release Plans

Name Invitations Review Week Test Week Release Planning Document
July-August Cycle (4.7.10) July 5 - 10 July 11 - 19 July 20 - July 29 July 3, 2016 Google Doc, JIRA Board, Calendar
June-July Cycle (4.7.9) June 9 - 14 June 14 - 25 June 27 - July 3 July 6, 2016 Google Doc
May-June Cycle (4.7.8) May 5 - 10 May 10 - 18 May 21 - 29 June 1, 2016 Google Doc
April-May Cycle (4.7.7) Apr 5 - 8 Apr 9 - 18 Apr 22 - May 1 May 4, 2016 Google Doc
  • Invitations: The release-manager curates the list of pending PRs and invites developers to partner-up based on related topics (such as a "CiviMail" group or a "CiviContribute" group). All members of the core developer team will participate.
  • Review Week: Participants review each other's PRs. This may involve some discussion, code-review, testing, merging, or closing PRs.
  • Test Week: Participants install the release-candidate with realistic configurations (eg staging sites) and check that their major customizations still work. Emergency issues (regressions) may be fixed.

(Note: This is a new process and may change for future releases.)

Philosophy

Reviewing and testing are natural, important, on-going parts of software-development, but they generally cannot be done by the original developer. All developers have a shared interest in having their changes reviewed by a neutral and competent party. The goal of the release-cycle is to match-up developers who are willing to check each other's work, and to bring in feedback from non-developers to improve quality assurance.